September 2014
Underground Construction

Underground construction is underway as planned.


May 2014
Piling Work

Piling work and foundation progressed with minor delay due to street protest.


March 2014
Ground Breaking Ceremony

Management of KLASS held groundbreaking ceremony at construction site.


December 2013
EIA Approved

KLASS Langsuan has been EIA approved. The project construction will commence in Q1, 2014. 


October 2013
Submission of the Environmental Impact Assessment (EIA)

EIA proposal has been submitted to the committee of the Environmental Impact Evaluation Bureau (EIEB) on 28 October.


October 2013
KLASS Langsuan sales office opened at The Portico

If you have chance to visit your future home at KLASS Langsuan, our new sales office at the Portico is opened to welcome you everyday from 10 am to 6 pm. 

Our sales consultants at the office will assist you with all issues related to your valuable property.  Please drop by or call us at  Tel 02-652-2992 for assistance.




       
      TEL. 02 392 2115-6, 082 422 5444   |    © KLASS CONDO All Rights Reserved.                                 Return to main page www.klasscondo.com