October 2014
Architectural Work Completed
Architectural work is 100% completed, interior decoration has been underway with 20% advancement. Maintenance and engineering is done by 40%.
|
|
|
September 2014
…And Continues…
Exterior, maintenance and engineering work is 80% done, interior works commences.
|
|
|
May 2014
Construction Continues
Building structure has now reached level 5, architect works / M&E works are processing at level 1. |
|
|
March 2014
Above Ground
Underground work is finished, above ground contruction begins. |
|
|
October 2013
Pile works completed, the second phase of foundation begins
In mid September, the concrete pile works completed as scheduled and smoothly followed by the second phase of underground foundation work which will involve making the soil protection around the site, soil excavating and placing the first concrete layer in the lower basement level. |
|
|
Jun 2013
Ground Breaking Ceremony
Management of KLASS held groundbreaking ceremony at construction site. |
|
|
May 2013
Building Demolition and Land Clearing
Demolition and land clearing is 80% completed, expect to finish by month end. |
|
|
May 2013
Building Construction
a. We are in the process of applying for the building construction permit at the Department
of Public Works, Town and Country Planning.
b. Bored foundation pile system is expected to move into the site and start off around
June, 2013. |
|
|
March 2013
EIA Approved
KLASS Silom has been EIA approved. The area will be cleared starting April 2013 and project construction will commence in Q2, 2013. |
|
|
December 2012
KLASS Silom Sales Office Opens
KLASS sales office officially opens its doors to clients on G floor, United Center Building, Silom Road. |
|
|
9-10 November 2012
Pre-Sales Event
Only on November 9-10, 2012, be one of the lucky few to receive Samsung Galaxy SIII with your purchase at the Pre-Sales Event. Two days only. Be first! |
|
|
|